Guide

Old Buildings and AREI Part 8: Special Rules for Existing Installations

What applies to older electrical installations in Belgium. AREI Part 8 explained: permitted deviations, periodic inspection, and tips for gradual modernisation.

Published on 14 April 2026 8 min min read

Old Buildings and AREI Part 8: Special Rules for Existing Installations

Not every electrical installation in Belgium needs to comply with the latest AREI/RGIE regulations. For older buildings, Part 8 (Partie 8) provides a dedicated set of rules that tolerates certain deviations from the current standard — as long as no immediate danger exists. This article explains when Part 8 applies, what is permitted, and where the limits lie.


What Is Part 8?

Part 8 of the AREI (Algemeen Reglement op de Elektrische Installaties / Règlement Général sur les Installations Électriques) is a special regulation for existing installations that were constructed and approved before the current AREI came into force.

The basic principle: as long as an installation functions safely and poses no immediate danger, it does not need to be fully brought up to the latest standards — even if it does not meet all current requirements.

Important: Part 8 is not a free pass. It clearly defines which deviations are tolerated and which are not.


When Does Part 8 Apply?

Part 8 applies to installations that meet one of the following conditions:

Condition 1: Installation Before 01.10.1981

Installations constructed before 1 October 1981 (the date the original AREI came into force) fall under Part 8 by default.

Condition 2: Approved Under the Old AREI

Installations that were approved under a previous version of the AREI and have not been substantially modified since the last approval.

What Counts as a "Substantial Modification"?

  • Adding new circuits
  • Expanding the distribution board
  • Modifying the metering installation
  • Extensive rewiring

Note: Small changes such as replacing a socket outlet or switch do NOT count as a substantial modification.


What Is Permitted Under Part 8? (Tolerated Deviations)

The following points deviate from the current AREI but are tolerated under Part 8 during inspection:

1. Old Cable Types

Current AREIPart 8 tolerates
XVB / VOBst in PreflexVOB cables in old conduits
Cca fire reaction classOlder cable types without CPR classification
Minimum cross-section 2.5 mm² for socketsMinimum 1 mm² with max. 6A fuse or 10A MCB (Art. 8.2.1 Nr. 5)

2. Residual Current Devices (RCD)

Current AREIPart 8 tolerates
30 mA RCD per socket circuitNo 30 mA RCD needed (only 300 mA main RCD)
30 mA RCD mandatory for bathroomTolerated without, if no direct risk
Max. 8 circuits per RCDMore circuits permitted

Note: Even under Part 8, a 300 mA main RCD is recommended and often required by the grid operator when a new meter is installed.

3. Socket Outlets Without Earth Contact

Old socket outlets (type C, without earth pin) are tolerated under Part 8, provided that:

  • No Class I appliances (with metal housing) are connected.
  • The socket is not in the bathroom or in a damp location.
  • The circuit is otherwise intact.

4. No SPD (Surge Protection)

The current AREI requires a Type 2 SPD (Surge Protection Device) for new installations. Under Part 8, this is not required.

5. Old Distribution Technology

  • Fuses instead of MCBs are permitted.
  • Screw-type fuses (Diazed) are tolerated.
  • Missing labelling is noted as a deficiency but does not cause a failure.

6. No Fire Reaction Classification of Cables

Cables without CPR classification (installed before 2017) are tolerated, as the CPR regulation only applies from July 2017 for new installations.


What Is NOT Permitted (Even Under Part 8)?

Certain conditions are never tolerated, regardless of the installation's age:

Absolutely Impermissible:

ConditionWhy?
Bare or damaged cablesImmediate electrocution risk
Complete absence of earthingNo protection in case of insulation fault
Water in contact with electricsDanger to life
Accessible live partsDirect contact risk
Overheated cables or connectionsFire risk
Loose connections in junction boxesArc/fire risk
Junction boxes without coversContact protection missing
Bathroom socket in zone 0 or 1Danger to life, prohibited even under Part 8

Even under Part 8, the following must be ensured:

  • Adequate cross-section for the actual load (no overloaded 0.75 mm² cable).
  • Functioning fuses (no "bridged" fuses).
  • Earthing of the main board (connection to earth electrode).
  • Accessibility of the distribution board.

Periodic Inspection

Every 25 Years Mandatory

Existing installations under Part 8 must undergo a periodic inspection every 25 years by an approved control body.

On Change of Ownership

When selling a property, a valid inspection certificate (less than 25 years old) is mandatory. If none exists, an inspection must be carried out before the sale.

18-month deadline (Art. 8.4.2.2): When purchasing a property with a negative inspection report, the buyer has 18 months from the purchase date to remedy the defects and have a re-inspection carried out.

What Is Checked During the Periodic Inspection?

Inspection PointAssessment
Visual inspection of cables and connectionsDamage, overheating
Earth resistance measurement≤ 30 Ohm (regulatory threshold per Art. 4.2.4.3b; above this, additional protective measures required)
Insulation resistance measurement> 0.5 MOhm
RCD test (if present)Trip time and current
Short-circuit protection checkFuses / MCBs present
Protection against direct contactCovers, IP protection
DocumentationSingle-line diagram + situation plan present?

Note: Even under Part 8, a single-line diagram and a situation plan must be available — even if they need to be created retrospectively.


The Contamination Rule for Partial Renovations

A particularly important aspect for old buildings: the so-called contamination rule.

How Does It Work?

When you substantially modify part of your installation (e.g., adding new circuits):

  1. The new part must fully comply with the current AREI.
  2. The existing part continues to be assessed under Part 8.
  3. BUT: If the new part "contaminates" the existing part (e.g., new cables in the same distribution board), the inspector may decide that the entire board must comply with the current AREI.

Practical Consequences:

  • Plan renovations so that new and old parts are clearly separated.
  • Ideally, use a separate sub-board for new circuits.
  • Document precisely what is old and what is new.

Recommendation: Gradual Modernisation

Even though Part 8 tolerates deviations, gradual modernisation is recommended:

Priority 1 (Safety-Critical)

  • Retrofit a 300 mA main RCD (if not present)
  • Replace damaged cables
  • Fix loose connections
  • Check and improve earthing if necessary
  • 30 mA group RCDs for bathroom and kitchen
  • Replace old fuses with MCBs
  • Retrofit SPD Type 2

Priority 3 (Comfort + Future-Proofing)

  • Modernise the board (more rows, labelling)
  • Retrofit socket outlets with earth
  • Preparation for EV charger / PV system

Cost Orientation

MeasureEstimated Cost
Retrofit 300 mA main RCDEUR 150–300
30 mA group RCD (each)EUR 80–150
SPD Type 2EUR 100–250
MCB set (10 pieces)EUR 50–100
New 4-row board (complete)EUR 500–1,500
Complete rewiring (house)EUR 5,000–15,000

Summary

QuestionAnswer
Does my old building need to comply with the current AREI?Not fully, Part 8 permits deviations
Do I need a 30 mA RCD?Not mandatory under Part 8, but strongly recommended
Are old sockets without earth permitted?Under conditions yes (no bathroom, no Class I appliances)
How often must inspections take place?Every 25 years + on change of ownership
What about partial renovation?New part = current AREI, old part = Part 8 (contamination rule applies)


Even for old buildings, PlanElec creates standards-compliant single-line diagrams and situation plans — the mandatory documents for every inspection. Document your installation digitally now. Start for free →