FAQ

Preflex vs. Open Wiring: Which Cable Method for Your Project?

Preflex conduit or XVB installed directly? Comparison for new builds and renovations in Belgium, with the AREI/RGIE rules on conduits, fire classes and installation zones.

Published on 27 March 2026 Updated on 6 November 2026 5 min

In new builds, Preflex with VOB wires is the Belgian standard: the conduits go onto the slab or into the walls during the shell phase, and the wires stay replaceable later. In renovations, XVB cable without conduit is usually the faster option, in a wall chase, surface-mounted or in a cavity. The AREI/RGIE permits both methods; it governs how you carry them out.

An electrician positions electrical conduits in an unfinished building.

What is Preflex?

In Belgium, Preflex is the common name for flexible corrugated plastic electrical conduit. It comes empty or with factory-pulled VOB wires. In new builds, it is laid during the shell phase on the concrete slab, in the screed or in wall chases, and then cast in or plastered over.

Open wiring here means cables without conduit, usually XVB: directly in a chase under plaster, surface-mounted, on a cable tray or in building cavities.

Preflex and open wiring compared

CriterionPreflex with VOB wiresOpen wiring with XVB
Conductor typeSingle-core wire (H07V-U/-R) in conduitSheathed cable
Typical useNew build, major renovationRenovation, basement, plant room, extension
Replacing wires lateryes, wires must remain pullable at all times (5.2.9.3)only by opening up or using a new route
Surface mountingonly the conduit, not the bare wire (5.2.9.5)yes (5.2.9.5)
Directly in a chasenot applicableyes, within the installation zones (5.2.9.10)
Materialconduit plus each wire separatelyone cable with all cores
Two wall sections. Left, a Preflex conduit with three VOB cores, embedded at least 3 cm deep; right, an XVB cable straight in the chase under at least 0.4 cm of plaster. Below, the rules from 5.2.9.3 and 5.2.9.10.
In conduit the cores stay replaceable; without conduit only a cable is allowed, and it must stay within the installation zones.
Open full-size image

What the AREI requires for conduits

Subsection 5.2.9.3 governs installation in electrical conduits:

  • Diameter: conduits and fittings sized so that conductors can easily be pulled in and removed after installation (letter d).
  • Bending radius: at least eight times the outside diameter for flexible thermoplastic conduit (letter e).
  • No joints in the conduit: connections belong in pull or junction boxes on a suitable terminal block (letter f).
  • Combustible conduit: permitted only if embedded at least 3 cm deep in non-combustible materials (letter f).
  • Heat: no thermoplastic conduit where the temperature can exceed 60 °C in normal operation (letter f).
  • Embedded conduit: no tees or elbows; conductors remain accessible in the boxes (letter i.2).

The AREI sets no fill limit as a percentage. The test is that conductors can be pulled in and removed at any time.

What the AREI requires for open wiring

Wiring embedded without conduit must be cable; conductors with basic insulation only are prohibited there (5.2.9.10). In the walls of rooms, installation zones apply: horizontal runs 25 to 35 cm below the ceiling or above the floor, vertical runs as close as possible to a corner or 10 to 20 cm beside door frames, and at least 0.4 cm of plaster cover. In concrete or cement, you need at least 3 cm of cover.

Which fire class do you need?

What counts is the CPR class of the cable, not of the conduit:

  • Installed singly: at least F1 or class Eca (5.2.7.2).
  • In bundles or flat formation: at least F2 or class Cca (5.2.7.3).
  • In building cavities: also F2 or Cca (4.3.3.5 b and 5.2.9.9). A timber-frame or plasterboard stud wall is a building cavity.

Cables and conduits embedded at least 3 cm deep in non-combustible cladding are exempt (5.2.7.1 no. 3). If the Preflex conduit sits at least 3 cm deep in concrete or screed, this exemption applies. In a cavity, by contrast, the class of cable and conduit counts (5.2.9.9 with 5.2.7.3 and 5.2.7.4).

Which method when?

  • New build: Preflex with VOB wires, cast into or plastered into floors and walls.
  • Renovation with chases: XVB directly in the chase, within the installation zones.
  • Basement, garage, plant room: XVB surface-mounted or on a cable tray.
  • Timber frame, drywall, suspended ceiling: cable rated at least Cca or a suitable conduit system.
  • Partial renovation: combine both; new circuits in Preflex, existing wiring kept after inspection.

For the cable types, see XVB cable or VOB wire; for the complete system, Installation methods under AREI.

New build with Preflex or renovation with open wiring: in PlanElec Sketch you draw the single-line diagram and situation plan for free in the browser and record type, fire class, installation method and In conduit for every cable; both export as PDF. PlanElec Pro checks more: the self-check flags cables in hollow walls below Cca without documented conduit (what the self-check verifies).

Regulatory basis: AREI/RGIE Book 1, version 06, subsections 4.3.3.5, 5.2.7.1–5.2.7.3, 5.2.9.3, 5.2.9.5, 5.2.9.9 and 5.2.9.10. Official text: FPS Economy.

Check your cable choice right away

Run load, length, supply network and protection through the cable calculator, then carry the circuit into your PlanElec project.

Fictitious sample dossier, available without sign-up.