Guide

Renovation and AREI: When Do You Need New Electrical Plans?

Not every renovation requires new electrical plans. Learn which works trigger a mandatory re-inspection and what the contamination rule means.

Published on 20 July 2026 8 min

When does a renovation trigger a mandatory re-inspection?

Not every renovation requires new electrical plans and a re-inspection. The AREI clearly distinguishes between works that trigger a mandatory re-inspection (keuring) and those that don't. This guide explains which rule applies to your renovation.

The decision tree: Re-inspection yes or no?

Re-inspection REQUIRED

The following works trigger a mandatory re-inspection (Art. 6.4.7.3):

WorkReason
Adding new circuitsExtension of the installation
Replacing the distribution boardChange to protection devices
Installing a sub-distributionExtension of the installation
Running new cablesSubstantial modification
Modifying the earthing systemSafety-critical
Converting to three-phaseFundamental change
Connecting an EV charger / heat pumpNew dedicated circuit

Re-inspection NOT REQUIRED

These works count as maintenance and don't trigger a re-inspection:

WorkWhy no re-inspection
Like-for-like socket/switch replacementSame position, same rating
Replacing a lamp with LEDNo intervention in the installation
Painting, wallpapering, flooringCosmetic, no electrical connection
Like-for-like breaker replacementSame type and rated current
Changing a socket cover plateNo intervention in wiring

Grey area: Moving a socket to a different position already counts as a modification. Any significant modification or extension triggers a re-inspection (Art. 6.4.7.3) — even if the circuit stays the same.

The contamination rule

The contamination rule is the most important concept for renovations:

If you modify one part of the installation, the inspector can question the entire installation.

What this means in practice

Say you renovate your bathroom and install new sockets and lighting:

  1. The bathroom is assessed against the current AREI — all current regulations apply
  2. The inspector can also check the rest of the installation
  3. Existing defects (e.g., missing RCDs in the basement) can also be flagged

How to limit contamination

  • Document precisely which parts were modified and which weren't
  • Mark the new/modified circuits in the single-line diagram
  • Unmodified parts fall under Part 8 (relaxed requirements)

Part 8 vs. Full AREI: What applies when?

The AREI distinguishes between old and new:

Installation partApplicable regulationRequirements
Unmodified, pre-1981Part 8 Art. 8.2 (existing installation)Relaxed — e.g., no RCD per circuit required, old cable types tolerated
Unmodified, 1981–2020Part 8 Section 8.2.2 (deviations for domestic installations under former A.O.E.A.)Must comply with the regulation at the time, with limited relaxations per Art. 8.2.2
Modified / NewCurrent AREIAll current requirements (300 mA main RCD + 30 mA high-sensitivity RCD for socket, lighting and bathroom circuits, SPD for the new/modified part, cable standards)

Typical scenario: 1960s house

You're renovating the kitchen and bathroom of a 1965 house:

  • Kitchen + bathroom (new circuits): Full current AREI — SPD expected as good practice (Art. 4.5.1, general principle; applies only to the new/modified part of the installation), 300 mA main RCD for the entire installation (Art. 4.2.4.3) + 30 mA high-sensitivity RCD for socket, lighting and bathroom circuits (Art. 4.2.4.3 point b), current cable types
  • Bedrooms, living room (unmodified): Part 8 — old VOB cables tolerated, no RCD per circuit required
  • However: If the inspector finds that the old installation poses a direct safety risk (e.g., exposed wires, missing earthing), they can still require remediation

Documentation for renovations

Houses with existing plans

If a current single-line diagram and situation plan exist:

  1. Update the plans — add new circuits, modified positions
  2. Mark clearly what is old and what is new
  3. Present updated plans to the inspector

Houses without plans (pre-1981)

Many older houses have no existing documentation. In that case (Art. 9.1.2):

  1. Survey the entire installation — including unmodified parts
  2. Create a complete new single-line diagram — for the entire installation
  3. Create a situation plan — draw all sockets, switches, lighting points

Warning: This is one of the most common reasons renovations become significantly more expensive than planned — the documentation requirement for the entire installation.

Budget planning: Typical costs

ItemCost
Single-line diagram + situation plan (electrician)€300 – €600
Single-line diagram + situation plan (PlanElec)Early Access currently free
AREI inspection€125 – €170
Re-inspection (if defects found)€80 – €120
Defect remediation€500 – €5,000+

The PlanElec advantage for renovations

With PlanElec, you can:

  • Document the existing installation
  • Add new circuits and have them automatically validated
  • Clearly separate old vs. new
  • Export the result as PDF for the inspector
  • Early Access currently free; payment processing is not active yet

Checklist for renovators

Before starting renovations:

  • Check: Do my works trigger a re-inspection?
  • Find existing electrical plans (if available)
  • Budget for documentation + inspection
  • Involve an electrician early (for the installation work)
  • Use PlanElec for documentation (create plans yourself)

After renovation:

  • Updated plans created?
  • All new circuits in the single-line diagram?
  • Inspection body contacted?
  • Inspection passed?

Plan your renovation AREI-compliant with PlanElec →