Getting started

Plan an installation and form distribution boards

Assign existing floor-plan devices, check protection paths and develop an electrical plan into distribution boards, cabinet layouts and a single-line diagram.

9 minUpdated October 07, 2026

In Installation, you plan which protective device supplies each circuit and its consumers. You use devices already placed in the floor plan. An enclosure and fixed module positions are not required yet. You can then form distribution boards, detail their cabinet layouts and review the resulting single-line diagram.

This guide follows one fictional home in the same project file. Its screenshots show real views of that example in the application. The sequence provides a starting point; existing projects and other valid planning approaches remain supported. A planning view or an exported draft does not establish electrical safety.

Quick start: from distribution board to topology

  1. Place loads and a distribution board on the floor plan.
  2. Select the board and Complete installation automatically. The same action is available in Installation.
  3. Review the target board, new circuits, protection devices and required space. Apply proposal adds the plan and opens the board’s topology.
  4. Open the cabinet view to inspect the prepared layout.

All unassigned loads without an assignment to another board are included. Existing circuits, cable data and module positions are preserved. An unconfigured cabinet receives an enclosure proposal; insufficient space in an existing enclosure is reported. Devices that require manual planning and missing feeder data remain open. One undo step reverses the operation. If the project changes, review the refreshed proposal before applying it. The preview lists every planned assignment by room with circuit, protection device and RCD. An empty circuit whose name matches the load is reused instead of adding another protection device.

The following sections explain manual editing and installation review.

What is each view for?

ViewWhat you plan here
Floor plan / situation planDevice positions and physical cable routes
InstallationSupply, protection paths, circuits and board boundaries
CabinetConcrete devices, enclosure, rows and module positions
Single-line diagramDocument representation of the same electrical installation
ExportDocuments from the saved project version with a visible review status

Assign an existing floor-plan device

  1. Place devices in the floor plan or open an existing project. See place and connect electrical symbols.
  2. Open Installation, search for the device and select it in the tree or graphical view.
  3. Click Assign circuit, choose the existing target circuit and confirm.
  4. Check the displayed protection path. The floor-plan link takes you to the associated symbol.

This assigns the same device. Do not create another consumer just to see it in the diagram. In the example, the existing living-room socket receives its circuit assignment.

The same living-room socket in the floor plan after its electrical assignment.
The floor-plan symbol stays in place; its electrical assignment has been completed.
Open full-size image

Move loads in the circuit list

The Circuits view lists every final circuit by board and RCD, with its loads, the sum of the recorded power and the phase. Loads without a circuit are shown at the top.

  1. Open Installation and choose the Circuits view.
  2. Drag a load onto the target circuit. Its cables move with it.
  3. Undo reverts the step completely.

Only items connected directly to the circuit breaker can be moved; a junction box takes its loads with it. The room filter shows only circuits that supply the selected room. Without a mouse, select the load and use Assign circuit.

Circuit list of the example house with the main board and the upper-floor sub-board.
Each circuit is listed under its RCD with designation, rated current, phase and loads.
Open full-size image

Resolve open tasks

With nothing selected, the side panel lists open tasks – one line per problem, not per device.

TaskSolution in the side panel
Loads without a circuitAssign automatically opens the automatic planning proposal
Board open: electrically connected but not assigned to a boardForm board opens the preview for the whole chain from its top device

Below are actions for the whole installation. Balance phases spreads single-phase circuits more evenly across L1–L3 on a three-phase supply without moving module positions. Add missing cables creates only missing cables; existing cables and their data stay unchanged. Calculate cable routes fills in missing routes on the floor plan and leaves manually drawn routes unchanged.

Read the complete supply and protection path

Return to the installation. The grid connection, meter, protective devices, circuits and consumers remain reachable together. Select a consumer to see its path back to the supply. Device references and circuit labels help you compare the floor plan and diagram.

Use search, expand/collapse and the tree view for larger projects. A collapsed branch still exists. Control relationships, switching functions and bus assignments are additional relationships; they must not be treated as arbitrary supply connections.

Installation overview of the example home from supply chain to consumers.
The overview uses existing devices in the project.
Open full-size image

Continue without a chosen cabinet

An undecided board is a saveable draft state. Save and reload the project: the open assignment remains open instead of being silently attached to a main board.

StateNext step
Not electrically assignedChoose the supply or circuit
Electrically connected, board openPlan a suitable physical group
Board chosen, layout openCheck the feeder and detail enclosure and modules
Modules placedReview layout, electrical information and documents
An electrically planned installation section with its physical board still open.
An electrical connection does not mean that cabinet planning is complete.
Open full-size image

Form a distribution board from a selection

  1. Select related protective devices using individual tree checkboxes or multiple selection in the graphical view.
  2. Click Create a board from selection and give it a clear name.
  3. Read the preview: supply entry, modules, consumers outside the cabinet, existing board boundaries and affected placements.
  4. Confirm only a suitable selection. If the selection conflicts, the application explains why; adjust it before continuing.
Upper-floor distribution board preview showing entry point, modules and effects.
The selection rectangle alone does not create a saved board boundary.
Open full-size image

After confirmation, the protective devices belong to the new physical board. Its supplied sockets and lights remain outside the frame. Electrically downstream boards are not enclosures physically nested inside each other.

Confirmed distribution board with protective devices inside and consumers outside.
Physical board membership and the area supplied by that board have different meanings.
Open full-size image

Next, check the feeder: select the actual upstream protective device and enter cable information such as conductor count, cross-section and length. Confirm that connection explicitly. Grouping invents neither a protective device nor a feeder cable. Radial planning requires one unambiguous upstream supply path; local sources such as PV are handled separately.

What do removal and deletion change?

ActionEffect
Dissolve board groupingRemove the physical group; retain electrical devices for planning
Remove module placementRemove the row position; retain the electrical device
Delete an electrical deviceChange the electrical object and its affected connections

Read each preview or confirmation, then review the affected views. Related electrical changes can be followed with undo/redo.

Detail modules and enclosure

Open the cabinet from the selected distribution board. Existing devices are carried over and unplaced modules remain findable. Choose concrete modules, check their width in module units (TE) and plan the rows.

Enclosure planning shows the module requirement and uses your entered reserve and terminal/accessory allowance. Check mounting type, wiring space, heat dissipation and manufacturer conditions. With generic modules or missing information, the space requirement remains an estimate. A proposed enclosure is not approval for construction.

Cabinet editor with the selected distribution board and its enclosure planning.
Electrical assignment and row position are separately editable. Rearranging the same cabinet does not change the protection path.
Open full-size image

Review the single-line diagram and export documents

Open Single-line diagram. The same consumers, protective devices and boards appear in the document view. Check board-specific sheets and cross-references. The diagram is rendered from the project model; it is not a screenshot of the installation tree.

Single-line diagram derived from the shared project model.
Moving or zooming the topology view does not change PDF coordinates.
Open full-size image

Switch to Export, check the saved version and choose the required documents. Open assignments, cable information and reviews remain visible. A download offered as a draft remains a draft. Producing documents does not replace professional review or the official inspection.

Actual exported document from the saved example project.
The document uses the same devices. Its visible status describes its intended use.
Open full-size image

Read more: export documents and what the self-check verifies.

Work on a tablet, phone or with the keyboard

On narrow screens, the tree view takes priority. Use checkboxes and named actions for assignment and board grouping. Arrow keys move through the tree, Enter opens the selected item and Space selects an item for multiple selection.

Mobile tree view with the same devices and accessible planning actions.
The graphical view and the tree edit the same project.
Open full-size image

Important for electrical planning

These guides explain the software workflow. Have the design, installation and documents reviewed by a qualified electrician where needed; only an accredited inspection body performs the official inspection.

Continue reading